DAC provided construction management services for the followiing improvements at Blackhawk Park: - site grading, drainage and detention
- instllation of driveway
- installation of parking lot,
- installation of concessions building/picnic pavilion
- installation of restroom building
- new concrete walks
- football fields
- playground border and equipment
- drinking fountain
- site furnishings
- planting and irrigation
- field grading and hydromulching
- installation of water, sanitary and electrical utilities to the site

Park Name and Location
| Blackhawk Park, 9401 Fuqua
| | Contractor | Times Construction
| City of Houston Project No.
| WBS: F-504B07-0007-4
| City of Houston Contract No.
| 62041
| BSD Project Manager
| Clifford Perry
| Design Services
| Clark Condon Associates, Inc. (CCA)
| CCA Contacts
| Richard McNamara, Principal
| Construction Manager
| Davis Alliance Corporation (DAC)
| Contract Value
| $1,503,245 | | Duration | 210 | | NTP | May 22, 2006
| |